For today's report on the ongoing hive project, I share with everyone the progress of the ongoing hive borehole project. The project has achieved great progress, owing to the efforts of the many employees involved since its start. We are pleased and glad that the project is making good progress at this point.
Fortunately, the foundation for the columns and wall had already been established. The masons are anticipated to continue working with the concrete to create the pillars before being allowed to harden for a few days. The tank seat may be constructed after all of the pillars have dried. The carpenter and plumber are both eager to get started on their respective tasks in order to complete the job on time. The progress achieved on the continuing hive project in Ghana gives me hope.
In this second stage of the borehole project, we have now built the building that will house the tank. Today's effort ensured that the pillar is ready for the project's following stages. As the pillar was completed, the seat of the pillar to hold the tank was also completed and ready. The pillar's seat, however, will be filled with concrete. After then, it is expected to dry for a few days before moving on to the next phase. However, this moment signifies the end of the borehole's subsequent stage.
We wish to reaffirm to everyone that we've been working hard to ensure that the hive ecosystem helps individuals while also connecting with them. Thank you to everyone who helped us accomplish our goal of promoting the hive blockchain. Thanks to everyone for their continual support.
Project : Construction of borehole
Location : Chichibong (Ghana, West Africa)
Sponsor : @valueplan
Project manager : @mcsamm & @collinz
Changing lives with hive.